The Data Collection process
has already begun on the Belleview Bypass and Baseline Road
projects and will continue through September 2006. The design of
the roadways will begin in October 2005 and continue until
construction documents are complete in August 2007. Public
Workshops are tentatively scheduled for August 2006 and June
2007. Right-of-way acquisition and construction are not yet
scheduled.